Budget & Budgetary Control 17. G Ltd. manufactures two products called 'M' and 'N'. Both products use a common raw material Z. The raw material…
CA Intermediate · 4 - Cost and Management Accounting · RTP · January 2027
Budget & Budgetary Control 17. G Ltd. manufactures two products called 'M' and 'N'. Both products use a common raw material Z. The raw material Z is purchased @ ₹ 36 per kg from the market. The company has decided to review inventory management policies for the forthcoming year. The following forecast information has been extracted from departmental estimates for the year ended 31st March 2026 (the budget period): Product M Product N Sales (units) 28,000 13,000 Finished goods stock increase by year-end 320 160 Post-production rejection rate (%) 4 6 Material Z usage (per completed unit, net of wastage) 5 kg 6 kg Material Z wastage (%) 10 5 Additional information: Usage of raw material Z is expected to be at a constant rate over the period. Annual cost of holding one unit of raw material in stock is 11% of the material cost. The cost of placing an orders is ₹ 320 per order. The management of G Ltd. has decided that there should not be more than 40 orders in a year for the raw material Z. Required: (a) Prepare functional budgets for the year ended 31st March 2026 under the following headings: (i) Production budget for Products M and N (in units). (ii) Purchases budget for Material Z (in kgs and value). (b) Calculate the Economic Order Quantity for Material Z (in kgs). (c) If there is a sole supplier for the raw material Z in the market and the supplier do not sale more than 4,000 kg. of material Z at a time. Keeping the management purchase policy and production quantity mix into consideration, calculate total quantity & material Z that can be available for production.
Suggested Answer and Working Notes:
17. (a) (i) Production Budget (in units) for the year ended 31st March 2026 Product M Product N Budgeted sales (units) 28,000 13,000 Add: Increase in closing stock 320 160 No. good units to be produced 28,320 13,160 Post production rejection rate 4% 6% No. of units to be produced 29,500 14,000 (28,320 / 0.96) (13,160 / 0.94) (ii) Purchase budget (in kgs and value) for Material Z Product M Product N No. of units to be produced 29,500 14,000 Usage of Material Z per unit of production 5 kg. 6 kg. Material needed for production 1,47,500 kg. 84,000 kg. Materials to be purchased 1,63,889 kg. (1,47,500 / 0.90) 88,421 kg. (84,000 / 0.95) Total quantity to be purchased 2,52,310 kg. Rate per kg. of Material Z ₹ 36 Total purchase price ₹ 90,83,160 (b) Calculation of Economic Order Quantity for Material Z EOQ = √(2 × 2,52,310 kg. × ₹ 320) / (₹ 36 × 11%) = √(16,14,78,400 / ₹ 3.96) = 6,385.72 kg. (c) Since, the maximum number of order per year can not be more than 40 orders and the maximum quantity per order that can be purchased is 4,000 kg. Hence, the total quantity of Material Z that can be available for production: = 4,000 kg. × 40 orders = 1,60,000 kg.
Topics: Budgets and Budgetary Control
ICAI Exam Preparation & Marks Distribution Resources
Explore observed chapter marks, past papers, and topic-wise practice for CA Intermediate:
- CA Chapter-Wise Weightage and Historical Marks — Review observed paper coverage
- CA Intermediate Solved Past Papers & Question Bank — Practice chapter-wise previous exam questions
- ICAI CA Intermediate Revision Test Papers (RTP) & Mock Test Papers (MTP)
- More 4 - Cost and Management Accounting Practice Questions with Step-by-Step Solutions