The wages budget for the last period was based on a standard repair time of 30 minutes per unit and a standard wage rate of 50 per hour. The actual…
CA Intermediate · 4 - Cost and Management Accounting · MTP · May 2024
The wages budget for the last period was based on a standard repair time of 30 minutes per unit and a standard wage rate of 50 per hour. The actual data for the last period are as follows: Number of units = 30,000 Labour rate variance = 7,500 (A) Labour efficiency variance = Nil From the information find out the actual rate of wages per unit From the information find out the actual rate of wages per unit
Suggested Answer and Working Notes:
Correct Answer: Option (D)
Correct answer: D. 25.25.
Topics: Budgets and Budgetary Control
ICAI Exam Preparation & Marks Distribution Resources
Explore observed chapter marks, past papers, and topic-wise practice for CA Intermediate:
- CA Chapter-Wise Weightage and Historical Marks — Review observed paper coverage
- CA Intermediate Solved Past Papers & Question Bank — Practice chapter-wise previous exam questions
- ICAI CA Intermediate Revision Test Papers (RTP) & Mock Test Papers (MTP)
- More 4 - Cost and Management Accounting Practice Questions with Step-by-Step Solutions