Vivida Ltd. manufactures two products Ace eyeglasses & Sharp 1 eyeglasses using various types of materials and one grade of labour general optical…
CA Intermediate · 4 - Cost and Management Accounting · PYQS · September 2026
Vivida Ltd. manufactures two products Ace eyeglasses & Sharp 1 eyeglasses using various types of materials and one grade of labour general optical technicians who cut lenses, drill frames and align hinges. Shown below is an extract from the company's working papers for the next month's budget: | | Ace eye-glasses | Sharp eye-glasses | | | | | | Budgeted sales (in units) | 1,100 | 2,200 | | Standard labour hours allowed per unit of product at full productivity | 3 | 4.5 | Labour is paid at ₹ 30 per hour. Overtime premium is 60% and is payable only if a worker works for more than 45 hours a week. There are 110 direct workers. Assume that they can work on either product equally efficiently. Efficiency during normal working hours may be taken to be the same as in overtime hours also. The target productivity for the productive hours worked by the direct workers in actually manufacturing the products is 75%. In addition, the non-productive down-time is budgeted at 15% of the productive hours worked. There are four 5-day weeks in the budgeted period and it is anticipated that sales and production will occur evenly throughout the whole period. The following information is given: | | Ace eye - glasses | Sharp eye - glasses | | | | | | Opening Stock (units) | 125 | 140 | | Closing Stock | 5 day's sales | 4 day's sales | Calculate the Wages Budget for the direct workers, showing the quantities and values for the next month. (7 Marks)
Suggested Answer and Working Notes:
Answer (a) Working Notes: 1. Production Budget (in units) No. of working days = 4 weeks x 5 days = 20 days. Daily sales: Ace = 1,100/20 = 55 units, Sharp = 2,200/20 = 110 units. Closing stock: Ace = 5 days × 55 = 275 units. Sharp = 4 days × 110 = 440 units. | Particulars | Ace eyeglasses | Sharp eyeglasses | |---|---|---| | Budgeted Sales (units) | 1,100 | 2,200 | | Add: Closing Stock (5 days'/4 days' sales) | 275 | 440 | | Less: Opening Stock | (125) | (140) | | **Budgeted Production (units)** | **1,250** | **2,500** | 2. Standard Labour Hours for Budgeted Production | Particulars | Ace eyeglasses | Sharp eyeglasses | Total | |---|---|---|---| | Budgeted Production (units) | 1,250 | 2,500 | | | Standard hours per unit (at full productivity) | 3 | 4.5 | | | Standard Hours (100% productivity) | 3,750 | 11,250 | 15,000 | | Productive Hours | 3,750/75% = 5,000 | 11,250/75% = 15,000 | 20,000 | | Non-Productive hours (15%) | 750 hours | 2,250 hours | 3,000 | | **Hours to be paid** | **5,750 hours** | **17,250 hours** | **23,000** | 3. Total Hours to be Paid | Particulars | Hours | |---|---| | Standard hours required at 100% productivity | 15,000 | | Productive hours to be worked (Std. hours /75% productivity) | 20,000 | | Add: Non-productive down-time (15% of productive hours) | 3,000 | | **Total Hours to be paid** | **23,000** | 4. Normal and Overtime Hours Normal available hours = 110 workers × 4 weeks × 45 hours per week = 19,800 hours. Since total hours to be paid (23,000) exceed normal available hours (19,800), Overtime hours = 23,000 – 19,800 = 3,200 hours Wages Budget for Direct Workers for the Next Month | Particulars | Hours | Rate (₹) | Amount (₹) | |---|---|---|---| | Normal hours wages | 19,800 | 30.00 | 5,94,000 | | Overtime hours - Basic wages | 3,200 | 30.00 | 96,000 | | Overtime hours - Premium (60% of basic) | 3,200 | 18.00 | 57,600 | | **Total Wages Budget** | **23,000** | | **7,47,600** | Total Wages Budget for Direct Workers for the next month = ₹ 7,47,600
Topics: Budgets and Budgetary Control
ICAI Exam Preparation & Marks Distribution Resources
Explore observed chapter marks, past papers, and topic-wise practice for CA Intermediate:
- CA Chapter-Wise Weightage and Historical Marks — Review observed paper coverage
- CA Intermediate Solved Past Papers & Question Bank — Practice chapter-wise previous exam questions
- ICAI CA Intermediate Revision Test Papers (RTP) & Mock Test Papers (MTP)
- More 4 - Cost and Management Accounting Practice Questions with Step-by-Step Solutions