What would be Prime cost from below information? Direct materials Purchased : ₹75,000 Direct labour : ₹45,000 Direct expenses : ₹15,000…
CA Intermediate · 4 - Cost and Management Accounting · MTP · September 2026
What would be Prime cost from below information? Direct materials Purchased : ₹75,000 Direct labour : ₹45,000 Direct expenses : ₹15,000 Manufacturing overheads : ₹22,500 Direct materials consumed : ₹67,500 What would be Prime cost from below information?
Suggested Answer and Working Notes:
Correct Answer: Option (B)
Correct answer: (B) ₹1,27,500.
Topics: Cost Sheet
ICAI Exam Preparation & Marks Distribution Resources
Explore observed chapter marks, past papers, and topic-wise practice for CA Intermediate:
- CA Chapter-Wise Weightage and Historical Marks — Review observed paper coverage
- CA Intermediate Solved Past Papers & Question Bank — Practice chapter-wise previous exam questions
- ICAI CA Intermediate Revision Test Papers (RTP) & Mock Test Papers (MTP)
- More 4 - Cost and Management Accounting Practice Questions with Step-by-Step Solutions