What would be Prime cost from below information? Direct materials Purchased :75,000Direct labour :45,000Direct expenses :15,000Manufacturing…

CA Intermediate · 4 - Cost and Management Accounting · MTP · May 2024
What would be Prime cost from below information? Direct materials Purchased :75,000Direct labour :45,000Direct expenses :15,000Manufacturing overheads :22,500Direct materials consumed :67,500

Options:

  1. ₹ 1,35,000
  2. ₹ 1,27,500
  3. ₹ 1,57,500
  4. ₹ 1,50,000

Suggested Answer and Working Notes:

Correct Answer: Option (B)

Correct answer: ₹ 1,27,500.

Topics: Overheads - Absorption Costing Method, Cost Sheet