The standard variable overhead cost of a product is 12, i.e. 6 hours at the rate of 2 per hour. In a certain month, it took 2,400 hours at a cost of…
CA Intermediate · 4 - Cost and Management Accounting · MTP · January 2026
The standard variable overhead cost of a product is 12, i.e. 6 hours at the rate of 2 per hour. In a certain month, it took 2,400 hours at a cost of 5,800 to manufacture 450 units. The variable overhead expenditure and efficiency variances, respectively, are:
Suggested Answer and Working Notes:
Correct Answer: Option (B)
Correct answer: ₹ 1,000 (A) and - 600 (F).
Topics: Overheads - Absorption Costing Method
ICAI Exam Preparation & Marks Distribution Resources
Explore observed chapter marks, past papers, and topic-wise practice for CA Intermediate:
- CA Chapter-Wise Weightage and Historical Marks — Review observed paper coverage
- CA Intermediate Solved Past Papers & Question Bank — Practice chapter-wise previous exam questions
- ICAI CA Intermediate Revision Test Papers (RTP) & Mock Test Papers (MTP)
- More 4 - Cost and Management Accounting Practice Questions with Step-by-Step Solutions