Standard Costing 15. BabyMoon Ltd. uses standard costing system in manufacturing one of its product 'Baby Cap'. The details are as follows: Direct…

CA Intermediate · 4 - Cost and Management Accounting · RTP · January 2027
Standard Costing 15. BabyMoon Ltd. uses standard costing system in manufacturing one of its product 'Baby Cap'. The details are as follows: Direct Material 1 Meter @ ₹ 60 per meter ₹ 60 Direct Labour 2 hour @ ₹ 20 per hour ₹ 40 Variable overhead 2 hour @ ₹ 10 per hour ₹ 20 Total ₹ 120 During the month of August, 10,000 units of 'Baby Cap' were manufactured. Details are as follows: Direct material consumed 11,400 meters @ ₹ 58 per meter Direct labour Hours ? @ ? ₹ 4,48,800 Variable overhead incurred ₹ 2,24,400 Variable overhead efficiency variance is ₹ 4,000 A. Variable overheads are based on Direct Labour Hours. You are required to CALCULATE the following Variances: (a) Material Variances- Material Cost Variance, Material Price Variance and Material Usage Variance. (b) Variable Overheads variances- Variable overhead Cost Variance, Variable overhead Efficiency Variance and Variable overhead Expenditure Variance. (c) Labour variances- Labour Cost Variance, Labour Rate Variance and Labour Efficiency Variance.

Suggested Answer and Working Notes:

15. (i) Material Variances Budget Std. for actual Actual Quantity (Meter) Price (₹) Amount (₹) Quantity (Meter) Price (₹) Amount (₹) Quantity (Meter) Price (₹) Amount (₹) 1 60 60 10,000 60 6,00,000 11,400 58 6,61,200 Material Cost Variance = (SQ × SP – AQ × AP) = 6,00,000 – 6,61,200 = ₹ 61,200 (A) Material Price Variance = (SP – AP) AQ = (60 – 58) 11,400 = ₹ 22,800 (F) Material Usage Variance = (SQ – AQ) SP = (10,000 – 11,400) 60 = ₹ 84,000 (A) (ii) Variable Overheads variances Variable overhead cost Variance = Standard variable overhead - Actual Variable Overhead = (10,000 units × 2 hours × ₹ 10) – 2,24,400 = ₹ 24,400 (A) Variable overhead Efficiency Variance = (Standard Hours - Actual Hours) × Standard Rate per Hour Let Actual Hours be 'X', then: (20,000 – X) × 10 = 4,000 (A) 2,00,000 – 10X = - 4,000 X = 2,04,000 ÷ 10 Therefore, Actual Hours (X) = 20,400 Variable overhead Expenditure Variance = Variable Overhead at Actual Hours - Actual Variable Overheads = 20,400 × ₹ 10 – 2,24,400 = ₹ 20,400 (A) (iii) Labour variances Budget Std. for actual Actual Hours Rate (₹) Amount (₹) Hours Rate (₹) Amount (₹) Hours Rate (₹) Amount (₹) 2 20 40 20,000 20 4,00,000 20,400 22* 4,48,800 *Actual Rate = ₹ 4,48,800 ÷ 20,400 hours = ₹ 22 Labour Cost Variance = (SH × SR) – (AH × AR) = 4,00,000 – 4,48,800 = ₹ 48,800 (A) Labour Rate Variance = (SR – AR) × AH = (20 – 22) × 20,400 = ₹ 40,800 (A) Labour Efficiency Variance = (SH – AH) × SR = (20,000 – 20,400) × 20 = ₹ 8,000 (A)

Topics: Standard Costing

ICAI Exam Preparation & Marks Distribution Resources

Explore observed chapter marks, past papers, and topic-wise practice for CA Intermediate:

Open in Interactive Practice Hub · Full Practice Hub · More in this subject