eX Precision Engineering Pvt. Ltd. operates a machine shop employing 35 workers, each working 8 hours per day including a 30-minute lunch break,…
CA Intermediate · 4 - Cost and Management Accounting · RTP · January 2027
eX Precision Engineering Pvt. Ltd. operates a machine shop employing 35 workers, each working 8 hours per day including a 30-minute lunch break, worked for 160 days during a period of six months ended on 31st December, 2025. The lunch break is unpaid and is not treated as working time. During this period, the total wages paid to these workers amounted to ₹2,52,000, which includes ₹30,000 paid as overtime premium and ₹12,000 paid as shift/production allowance — neither of which forms part of the basic wages. However, Dearness allowance and bonus of ₹42,000 and ₹21,000 respectively were paid at the end of the period. The management of the company decided the overtime premium rates for the month of January 2026 as under: Sundays and holidays 200% of basic wage rate Before and after normal working hours 150% of basic wage rate During the last six months (ended on 31st December, 2025), the following hours were worked: Particulars Hours Normal time 39,375 Sundays and holidays 525 Before and after normal working hours 2,100 Total hours 42,000 During the month of January 2026, the factory worked on a job AK-9 in the following manner: Particulars Men hours Normal working 1,680 Overtime on Sundays and holidays 140 Overtime before and after normal working 280 Total hours 2,100 DA and Bonus shall be included to arrive at basic wages. You are required to CALCULATE the labour cost chargeable to job AK-9 and overheads in each of the following situations: (i) Where overtime is worked regularly throughout the year as a matter of policy on account of shortage of workers. (ii) Where overtime is worked irregularly to cope with the general production programme / to meet the requirements of production. (iii) Where overtime is worked at the desire (request) of the customer to complete the job in time. (iv) Where overtime is worked on account of abnormal conditions such as earthquake in the area.
Suggested Answer and Working Notes:
Working Notes: 1. Calculation of Basic Wage Rate Effective (productive) working hours = 35 workers × (8 - 0.5) hrs per day × 160 days = 35 × 7.5 × 160 = 42,000 hours Basic wages = Total wages - Overtime premium - Shift/production allowance + DA + Bonus = ₹2,52,000 - ₹30,000 - ₹12,000 + ₹42,000 + ₹21,000 = ₹2,73,000 Basic wage rate = Basic wages ÷ Effective working hours = ₹2,73,000 ÷ 42,000 hours = ₹6.50 per hour Overtime rate (Sundays & holidays) = ₹6.50 × 200% = ₹13.00 per hour Overtime rate (before & after normal hrs) = ₹6.50 × 150% = ₹9.75 per hour 2. Computation of average inflated wage rate (including overtime premium) Particulars Amount (₹) Normal time (39,375 hrs × ₹6.50) 2,55,937.50 Overtime - Sundays & holidays (525 hrs × ₹13.00) 6,825.00 Overtime - before & after (2,100 hrs × ₹9.75) 20,475.00 Total wages for 42,000 hrs 2,83,237.50 Average inflated wage rate = 2,83,237.50 ÷ 42,000 hrs = ₹6.74 per hour Labour cost chargeable to Job AK-9 (2,100 hours) (i) Where overtime is worked regularly throughout the year as a matter of policy on account of shortage of workers: The overtime premium is treated as a part of employee cost and job is charged at an inflated wage rate. Employee cost chargeable to job = 2,100 hrs × ₹6.74 = ₹14,154 (ii) Where overtime is worked irregularly to cope with the general production programme / to meet the requirements of production: Basic wage rate is charged to the job and overtime premium is charged to factory overheads as under- Employee cost chargeable to Job = 2,100 hrs × ₹6.50 = ₹13,650 Factory overhead = {140 × (13.00 - 6.50)} + {280 × (9.75 - 6.50)} = ₹910 + ₹910 = ₹1,820 (iii) Where overtime is worked at the desire (request) of the customer to complete the job in time: The basic wage rate is charged to the job and overtime premium also charged to the job as under- Employee cost chargeable to Job = 2,100 hrs × ₹6.50 = ₹13,650 Overtime Premium = {140 × (13.00 - 6.50)} + {280 × (9.75 - 6.50)} = ₹910 + ₹910 = ₹1,820 Total = ₹13,650 + ₹1,820 = ₹15,470 (iv) Where overtime is worked on account of abnormal conditions such as earthquake in the area: Basic wage rate charged to the job and overtime premium is charged to Costing Profit & Loss Account as under- Employee cost chargeable to Job = 2,100 hrs × ₹6.50 = ₹13,650 Costing P&L A/c = {140 × (13.00 - 6.50)} + {280 × (9.75 - 6.50)} = ₹910 + ₹910 = ₹1,820 Total = ₹13,650 + ₹1,820 = ₹15,470
Topics: Employee Cost & Direct Expenses
ICAI Exam Preparation & Marks Distribution Resources
Explore observed chapter marks, past papers, and topic-wise practice for CA Intermediate:
- CA Chapter-Wise Weightage and Historical Marks — Review observed paper coverage
- CA Intermediate Solved Past Papers & Question Bank — Practice chapter-wise previous exam questions
- ICAI CA Intermediate Revision Test Papers (RTP) & Mock Test Papers (MTP)
- More 4 - Cost and Management Accounting Practice Questions with Step-by-Step Solutions