Sunrise Fabricators Ltd., a medium-sized engineering unit located in the Vadodara industrial belt, manufactures precision-machined components for…
CA Intermediate · 4 - Cost and Management Accounting · RTP · January 2027
Sunrise Fabricators Ltd., a medium-sized engineering unit located in the Vadodara industrial belt, manufactures precision-machined components for the automotive and pump industries. The company employs a team of skilled turners, fitters and machine operators in its machine shop, and the management strongly believes in linking a part of employee remuneration to individual efficiency. Accordingly, it operates premium-bonus incentive schemes to reward workers who complete their jobs in less than the standard time set by the rate-setting department. For its skilled workers, the company pays a guaranteed wage rate of ₹90 per hour. For a particular precision product, the rate-setting department has fixed a standard time of 4 hours per unit. Mr. R, an experienced turner in the machine shop, is at present remunerated under the Rowan Incentive Plan. On the manufacture of this product during the period, Mr. R earned an effective hourly rate of ₹112.50. As part of a periodic review of its incentive policy, the management wishes to compare the outcome under an alternative scheme. Had Mr. R been put on the Halsey Incentive Scheme (50%) instead, his total earnings and effective hourly rate respectively would be: (A) ₹315 and ₹105 (B) ₹270 and ₹90 (C) ₹337.50 and ₹112.50 (D) ₹360 and ₹120
Suggested Answer and Working Notes:
Total earnings (under 50% Halsey Scheme) = Hours worked × Rate per hour + ½ × time saved × Rate per hour = 3 hours × ₹90 + ½ × 1 hour × ₹90 = ₹315 Effective hourly rate = Total earnings ÷ Hours worked = ₹315 ÷ 3 = ₹105 Working Note: Let T hours be the total time worked (in hours) by the skilled worker (turner Mr. R); ₹90 is the rate per hour; the standard time is 4 hours per unit and the effective hourly earnings rate is ₹112.50, then - Earning (under Rowan Plan) = Time taken × Rate per hr + Time saved × Time taken × Rate per hr The final answer is 315 and 105.The final answer is $oxed{ ext{315 and 105}}$
Topics: Employee Cost & Direct Expenses
ICAI Exam Preparation & Marks Distribution Resources
Explore observed chapter marks, past papers, and topic-wise practice for CA Intermediate:
- CA Chapter-Wise Weightage and Historical Marks — Review observed paper coverage
- CA Intermediate Solved Past Papers & Question Bank — Practice chapter-wise previous exam questions
- ICAI CA Intermediate Revision Test Papers (RTP) & Mock Test Papers (MTP)
- More 4 - Cost and Management Accounting Practice Questions with Step-by-Step Solutions