In a factory, standard time for a job is 72 hours. The hourly-rate of wages is ₹60. Halsey Premium Plan is in operation at the factory. A worker…

CA Intermediate · 4 - Cost and Management Accounting · PYQS · September 2026
In a factory, standard time for a job is 72 hours. The hourly-rate of wages is ₹60. Halsey Premium Plan is in operation at the factory. A worker completes the job at less than standard time and his effective hourly-rate wages was ₹75. How many hours did he actually take to complete the work?

Options:

  1. (A) 60
  2. (B) 72
  3. (C) 48
  4. (D) 64

Suggested Answer and Working Notes:

Correct Answer: Option (C)

Correct Answer: (C) Working Notes / Reasoning: Standard Time (S) = 72 hours Hourly Rate (R) = ₹60 Effective Hourly Rate = ₹75 Let Actual Time Taken (T) be 'x' hours. Under Halsey Premium Plan, Total Earnings = (T * R) + (50% * (S - T) * R) Effective Hourly Rate = Total Earnings / Actual Time Taken ₹75 = [(x * ₹60) + (0.50 * (72 - x) * ₹60)] / x ₹75x = ₹60x + (0.50 * (72 - x) * ₹60) ₹75x = ₹60x + (30 * (72 - x)) ₹75x = ₹60x + ₹2,160 - ₹30x ₹75x = ₹30x + ₹2,160 ₹45x = ₹2,160 x = ₹2,160 / ₹45 x = 48 hours Therefore, the worker actually took 48 hours to complete the work. Correct answer: (C) 48.

Topics: Employee Cost & Direct Expenses

ICAI Exam Preparation & Marks Distribution Resources

Explore observed chapter marks, past papers, and topic-wise practice for CA Intermediate:

Open in Interactive Practice Hub · Full Practice Hub · More in this subject