In a factory, standard time for a job is 72 hours. The hourly-rate of wages is ₹60. Halsey Premium Plan is in operation at the factory. A worker…
CA Intermediate · 4 - Cost and Management Accounting · PYQS · September 2026
In a factory, standard time for a job is 72 hours. The hourly-rate of wages is ₹60. Halsey Premium Plan is in operation at the factory. A worker completes the job at less than standard time and his effective hourly-rate wages was ₹75. How many hours did he actually take to complete the work?
Suggested Answer and Working Notes:
Correct Answer: Option (C)
Correct Answer: (C) Working Notes / Reasoning: Standard Time (S) = 72 hours Hourly Rate (R) = ₹60 Effective Hourly Rate = ₹75 Let Actual Time Taken (T) be 'x' hours. Under Halsey Premium Plan, Total Earnings = (T * R) + (50% * (S - T) * R) Effective Hourly Rate = Total Earnings / Actual Time Taken ₹75 = [(x * ₹60) + (0.50 * (72 - x) * ₹60)] / x ₹75x = ₹60x + (0.50 * (72 - x) * ₹60) ₹75x = ₹60x + (30 * (72 - x)) ₹75x = ₹60x + ₹2,160 - ₹30x ₹75x = ₹30x + ₹2,160 ₹45x = ₹2,160 x = ₹2,160 / ₹45 x = 48 hours Therefore, the worker actually took 48 hours to complete the work.
Correct answer: (C) 48.
Topics: Employee Cost & Direct Expenses
ICAI Exam Preparation & Marks Distribution Resources
Explore observed chapter marks, past papers, and topic-wise practice for CA Intermediate:
- CA Chapter-Wise Weightage and Historical Marks — Review observed paper coverage
- CA Intermediate Solved Past Papers & Question Bank — Practice chapter-wise previous exam questions
- ICAI CA Intermediate Revision Test Papers (RTP) & Mock Test Papers (MTP)
- More 4 - Cost and Management Accounting Practice Questions with Step-by-Step Solutions