Reference Schedule: Quantity of Labour Total Product (TP) Average Product (AP) Marginal Product (MP) 1 10 10 10 2 22 11 12 3 36 12 14 4 44 11 8 5 45…

CA Foundation · 4 - Business Economics · PYQS · September 2025
Reference Schedule: Quantity of Labour Total Product (TP) Average Product (AP) Marginal Product (MP) 1 10 10 10 2 22 11 12 3 36 12 14 4 44 11 8 5 45 9 1 What will be the marginal product when the quantity of labour is 4?

Options:

  1. A. 26
  2. B. 20
  3. C. 10
  4. D. 19

Suggested Answer and Working Notes:

Correct Answer: Option (C)

Correct answer: C. 10.

Topics: Theory of Production and Cost