XYZ Ltd., a U.S. firm, will require £ 300,000 in 180 days and is evaluating different strategies to hedge against currency risk. The available…

CA Final · 2 - Advanced Financial Management · MTP · September 2025
XYZ Ltd., a U.S. firm, will require £ 300,000 in 180 days and is evaluating different strategies to hedge against currency risk. The available market data is as follows: Current Spot Rate: 1 £ = $ 2.00 180-Day Forward Rate: 1 £ = $ 1.96 Interest Rates: UK (180 days):Deposit Rate: 4.50%Borrowing Rate: 5.00%US (180 days):Deposit Rate: 5.00%Borrowing Rate: 5.50% Option Contract: Call option available on £, expiring in 180 days with:Exercise Price: $ 1.97Premium: $ 0.04 XYZ Ltd. has forecasted the following probabilities for spot rates after 180 days: Spot Rate Probability $ 1.91 25% $ 1.95 60% $ 2.05 15% From the information given above, choose the correct answer to the following questions: Part 1: The expected dollar amount needed.........if XYZ Ltd. does not hedge. (A) $ 5,88,000 (B) $ 6,05,741 (C) $ 5,95,560 (D) $ 5,86,500 Part 2: If XYZ Ltd. chooses the forward contract option, the expected dollar amount needed in 180 days, the total dollar amount required shall be......... (A) $ 5,88,000 (B) $ 6,05,741 (C) $ 5,95,560 (D) $ 5,86,500 Part 3: Under the money market hedge, approximately how much amount in dollars will XYZ Ltd. need to repay after 180 days? (A) $ 5,88,000 (B) $ 6,05,741 (C) $ 5,95,560 (D) $ 5,86,500 Part 4: If XYZ Ltd. chooses the call option contract, after 180 days the total cost in dollar for £ 300,000 (inclusive of interest on Premium amount) shall be........ (A) $ 5,88,000 (B) $ 6,05,741 (C) $ 5,95,560 (D) $ 5,86,500 Part 5: The expected spot rate per £ after 180 days shall be approximately......... (A) $ 1.91 (B) $ 1.94 (C) $ 1.96 (D) $ 2.05

Suggested Answer and Working Notes:

Part 1: Correct answer: $ 5,86,500. Part 2: Correct answer: $ 5,88,000. Part 3: Correct answer: $ 6,05,741. Part 4: Correct answer: $ 5,95,560. Part 5: Correct answer: $ 1.96.

Topics: Foreign Exchange Exposure and Risk Management

ICAI Exam Preparation & Marks Distribution Resources

Explore observed chapter marks, past papers, and topic-wise practice for CA Final:

Open in Interactive Practice Hub · Full Practice Hub · More in this subject