The following information is provided by the DVP Ltd. for the year ending 31st March, 2025. Raw Material storage period 50 days Work in progress…

CA Intermediate · 6 - Financial Management and Strategic Management · MTP · May 2026
The following information is provided by the DVP Ltd. for the year ending 31st March, 2025. Raw Material storage period 50 days Work in progress conversion period 18 days Finished Goods storage period 22 days Debt Collection period 45 days Creditors' payment period 55 days Number of Operating Cycle in a Year (360 days) of DVP Ltd is:

Options:

  1. 4.50
  2. 3.10
  3. 4.25
  4. 2.20

Suggested Answer and Working Notes:

Correct Answer: Option (A)

Correct answer: 4.50.

Topics: Part-A: Financial Management