A company's wage budget for the last month was based on a standard production time of 30 minutes per unit and a standard wage rate of 50 per hour. During the last month, it produced 30,000 units. The labour rate variance was - 7,500 adverse and the labour efficiency variance was nil. What is the actual wage rate per unit during the last month?

Options:

  1. ₹ 50.00
  2. ₹ 25.50
  3. ₹ 50.50
  4. ₹ 25.25

Suggested Answer and Working Notes:

Correct Answer: Option (D)

Correct answer: ₹ 25.25.

Topics: Standard Costing, Budgets and Budgetary Control