Pre-determined factory overhead rate was 15 per labour hour. Actual labour hour worked 60,000. Actual factory overhead was - 11,00,000 however it…
CA Intermediate · 4 - Cost and Management Accounting · MTP · May 2025
Pre-determined factory overhead rate was 15 per labour hour. Actual labour hour worked 60,000. Actual factory overhead was - 11,00,000 however it includes - 26,000 being the wages paid for strike period and overtime wages amounting to 9,000. It was observed that 2/3 of the under absorbed were due to inflation and rest were due to faulty planning. The amount of over/under absorbed factory overhead transferred to costing P&L will be:
Suggested Answer and Working Notes:
Correct Answer: Option (A)
Correct answer: 58,000 under-absorbed.
Topics: Employee Cost & Direct Expenses, Overheads - Absorption Costing Method
ICAI Exam Preparation & Marks Distribution Resources
Explore observed chapter marks, past papers, and topic-wise practice for CA Intermediate:
- CA Chapter-Wise Weightage and Historical Marks — Review observed paper coverage
- CA Intermediate Solved Past Papers & Question Bank — Practice chapter-wise previous exam questions
- ICAI CA Intermediate Revision Test Papers (RTP) & Mock Test Papers (MTP)
- More 4 - Cost and Management Accounting Practice Questions with Step-by-Step Solutions