A company is working in manufacturing sector and uses labour-force, which consists of skilled, semi-skilled, and unskilled workers. The rate of Labour per week for skilled worker is 120, for semi-skilled workers is 80and for unskilled worker is 60. It had planned the labour for a job that would take 60 weeks to be completed, ideally. Ratio of workers employed in skilled, semi-skilled, and unskilled would be 5:3:4. The management consultant who was employed to handle this job died in an accident. Board hired a new consultant to take over this job. This new consultant had a different approach for doing this job. He thought that workers actually required would be in the ratio of 7:3:8. He changed the composition of labour-force and employed the workers in the new ratio. Project was carried out successfully and it turned out that this change in Mix of labour-force saved the company - 76,800 in the job but at the same time company also lost - 1,29,600 due to poor productivity of the labourers. As a result, management consultant was promoted and labour force was fired & was replaced with more experienced labour-force. As the new management consultant was promoted, company found a new one to replace him. This 3rd management consultant was asked to understand and analyse the previous job done by the 2nd management consultant. Data in addition to above-given information was provided as follows:- Net extra cost spent, in comparison to planned cost, was - 1,04,000.Total number of weeks worked by all the type of labourers was 23,040 weeks.Skilled and semi-skilled labourers in reality charged 20extra per week, whereas unskilled labourers were negotiated to charge 20less per week, than what they had charged earlier. Let say, you are the 3rd management consultant, and you have been given with all this information. Work out calculations and answer the following questions (MCQs 6 to 10) based on the information given above. Part 1: If the total of labour efficiency variance of skilled and semiskilled labourers is 1,29,600 (Favourable), what is the labour efficiency variance of unskilled labour? (A) 1,82,400 (Adverse) (B) 52,800 (Adverse) (C) 1,29,600 (Adverse) (D) 76,800 (Favourable) Part 2: What are the amounts that company saved & paid extra to labourers, respectively? (A) 2,56,000 & 2,04,800 (B) 1,79,200 & 204,800 (C) 2,04,800 & 2,56,000 (D) 204,800 & 1,79,200 Part 3: If in total 1,440 weeks were worked in addition to what was planned, how many extra/less workers were used in actual, compared to standard? (Answer in sequence of skilled, semi-skilled, & unskilled). (A) -10, -30, -40 (B) -10, -30, +40 (C) +10, +30, -40 (D) +10, +30, +40 Part 4: Calculate revised standard weeks for all 3 types of labour forces? (Answer in sequence of skilled, semi-skilled, & unskilled). (A) 9,400, 5,650, & 7,990 (B) 9,550, 6,280, & 7,210 (C) 8,520, 6,850, & 7,670 (D) 9,600, 5,760, & 7,680 Part 5: If standard rates charged by skilled, semi-skilled, and unskilled were - 120,80, & ₹ 60, respectively, then which labour force performed worst, better, & best, due to change in labour composition? (A) Semi-skilled, skilled, & unskilled (B) Skilled, semi-skilled, unskilled (C) Unskilled, skilled, & semi-skilled (D) Unskilled, semi-skilled, & skilled

Suggested Answer and Working Notes:

Part 1: Correct answer: 1,82,400 (Adverse). Part 2: Correct answer: 2,04,800 & 2,56,000. Part 3: Correct answer: -10, -30, +40. Part 4: Correct answer: 9,600, 5,760, & 7,680. Part 5: Correct answer: Unskilled, skilled, & semi-skilled.

Topics: Standard Costing

ICAI Exam Preparation & Marks Distribution Resources

Explore observed chapter marks, past papers, and topic-wise practice for CA Intermediate:

Open in Interactive Practice Hub · Full Practice Hub · More in this subject