CA Intermediate · 4 - Cost and Management Accounting · PYQS · January 2025
ABC Company produces three products X, Y and Z. Similar type of material is used in the production of all the three products. The company has been using traditional absorption costing method, using direct labour hours to allocate overheads to its products. The Cost Accountant has suggested considering an activity based costing system. The following information is available in the records of the company. X Y Z Production Volume p.a. (In units) 16,000 17,000 15,000 Direct Material per unit 3 kg 4 kg 5 kg Labour hours per unit 0.10 0.15 0.20 Machine hours per unit 0.5 0.7 0.9 No. of Production runs p.a 50 65 60 No. of purchase orders p.a 5 10 15 No. of order shipped p.a 25 35 32 Activity Cost (₹) Cost Driver Machine setup costs 49,000 Production Runs Machine running costs 64,128 Machine hours Purchase cost 52,050 Purchase orders Delivery cost 46,460 Orders shipped The price of Raw Material is 2 per kg. Direct labour cost per hour is 20. On the basis of above Case Scenario, you are required to answer the following MCQs 1 to 5: Part 1: What is overhead absorption rate per hour as per traditional absorption costing method? (A) ₹ 29.60 (B) ₹ 29.32 (C) ₹ 13.78 (D) ₹ 15.82 Part 2: What is full cost per unit of product Y under traditional absorption costing method? (A) ₹ 19.92 (B) ₹ 4.44 (C) ₹ 46.32 (D) ₹ 15.44 Part 3: Under an activity based costing system, what is the cost driver rate for machine set up costs? (A) ₹ 280 (B) ₹ 1.467 (C) ₹ 6.85 (D) ₹ 230 Part 4: Under an activity based costing system, the amount of allocated overheads attributable to machine running hours to product X is: (A) ₹ 22,848 (B) ₹ 15,360 (C) ₹ 25,920 (D) ₹ 14,000 Part 5: The total cost of product Z as per activity based costing method is : (A) ₹ 2,86,073 (B) ₹ 2,94,905 (C) ₹ 84,905 (D) ₹ 2,60,660
Suggested Answer and Working Notes:
Part 1: Correct answer: ₹ 29.60.
Part 2: Correct answer: ₹ 15.44.
Part 3: Correct answer: ₹ 280.
Part 4: Correct answer: ₹ 15,360.
Part 5: Correct answer: ₹ 2,94,905.
Topics: Activity Based Costing, Overheads - Absorption Costing Method
ICAI Exam Preparation & Marks Distribution Resources
Explore observed chapter marks, past papers, and topic-wise practice for CA Intermediate:
- CA Chapter-Wise Weightage and Historical Marks — Review observed paper coverage
- CA Intermediate Solved Past Papers & Question Bank — Practice chapter-wise previous exam questions
- ICAI CA Intermediate Revision Test Papers (RTP) & Mock Test Papers (MTP)
- More 4 - Cost and Management Accounting Practice Questions with Step-by-Step Solutions